Pathways Project: August 20, 2026

Pathways construction progress continues!

-Framing has begun at the site, the community center building framing is completed.

-All foundations have been poured

-Building 1 electrical, plumbing and framing is nearing completion

-Framing progress has started at buildings 2 and 4

-Utility connections are in progress from the street into the site


Pathways Project: July 14, 2026

We are excited to share progress updates from Pathways Place in Ellensburg! Since construction began:

-The existing parking lot has been removed

-Trees on site have been evaluated and protected

-The interior of Nites Inn has been demoed and framing has been completed

-Building 2, 3, and 4 footings for the foundations have been poured

May 28

July 10