Want to learn more about Pathways Project in Ellensburg?


Pathways Place: November 18, 2026

Framing work continues at the Pathways site and some buildings are now in the roofing phase!


Teanaway Court: November 15, 2026

At the Teanaway site, foundations are still being poured and some buildings have entered the framing phase. Meanwhile, utility work connecting the site to sewer and water is also being completed


Pathways Place: November 5, 2026

Construction progress at Pathways in Ellensburg! Framing and roof work has been ongoing the past month and the site is looking brand new.


Teanaway Court: November 2, 2026

Framing is now underway at the Teanaway Court site in Cle Elum for the buildings that have foundations. Crews have gotten walls placed at several of the buildings, are finishing foundations on additional buildings, and the utility extensions are now being completed.


Teanaway Court: September 10, 2026

Construction has begun at the Teanaway Court site in Cle Elum. Crews are working hard to excavate the site, set forms, and get everything ready for the foundations to be poured before winter weather arrives.

Construction workers install a large concrete drainage pipe in a deep excavated trench using a green lifting frame and chains.
Construction site with excavated foundation trenches, wooden formwork, heavy equipment, safety fencing, homes, and pine trees under a blue sky

Pathways Project: August 20, 2026

Pathways construction progress continues!

-Framing has begun at the site, the community center building framing is completed.

-All foundations have been poured

-Building 1 electrical, plumbing and framing is nearing completion

-Framing progress has started at buildings 2 and 4

-Utility connections are in progress from the street into the site

Construction site with concrete building foundation, lumber, heavy equipment, and trees under a clear blue sky
Wood-framed house under construction with unfinished roof trusses and plywood walls on a sunny day
Interior of a new house under construction with exposed wood framing, roof trusses, concrete slab, and a ladder.

Pathways Project: July 14, 2026

We are excited to share progress updates from Pathways Place in Ellensburg! Since construction began:

-The existing parking lot has been removed

-Trees on site have been evaluated and protected

-The interior of Nites Inn has been demoed and framing has been completed

-Building 2, 3, and 4 footings for the foundations have been poured

Construction site with a reinforced concrete foundation, excavators, gravel, fencing, and trees beneath a clear blue sky
Construction site with concrete foundation walls, excavators, trees, mountains, and a blue sky with scattered clouds
Aerial view of a construction site beside commercial buildings, trees, homes, and distant hills

May 28

Multi-story building under construction with scaffolding and caution tape beneath a bright blue sky with clouds
Aerial view of a commercial construction site with building foundations, heavy equipment, surrounding neighborhood, trees, and distant rolling hills under a blue sky.

July 10