Want to learn more about Pathways Project in Ellensburg?
Pathways Place: November 18, 2026
Framing work continues at the Pathways site and some buildings are now in the roofing phase!
Teanaway Court: November 15, 2026
At the Teanaway site, foundations are still being poured and some buildings have entered the framing phase. Meanwhile, utility work connecting the site to sewer and water is also being completed
Pathways Place: November 5, 2026
Construction progress at Pathways in Ellensburg! Framing and roof work has been ongoing the past month and the site is looking brand new.
Teanaway Court: November 2, 2026
Framing is now underway at the Teanaway Court site in Cle Elum for the buildings that have foundations. Crews have gotten walls placed at several of the buildings, are finishing foundations on additional buildings, and the utility extensions are now being completed.
Teanaway Court: September 10, 2026
Construction has begun at the Teanaway Court site in Cle Elum. Crews are working hard to excavate the site, set forms, and get everything ready for the foundations to be poured before winter weather arrives.
Pathways Project: August 20, 2026
Pathways construction progress continues!
-Framing has begun at the site, the community center building framing is completed.
-All foundations have been poured
-Building 1 electrical, plumbing and framing is nearing completion
-Framing progress has started at buildings 2 and 4
-Utility connections are in progress from the street into the site
Pathways Project: July 14, 2026
We are excited to share progress updates from Pathways Place in Ellensburg! Since construction began:
-The existing parking lot has been removed
-Trees on site have been evaluated and protected
-The interior of Nites Inn has been demoed and framing has been completed
-Building 2, 3, and 4 footings for the foundations have been poured